Lighthouse developers say construction

would take eight to 10 years.

Phase I (4-5 years)

Installation of infrastructure: electricity, water, sewage systems

Coliseum (21/2 years)

Canal zone: Construction of canal lined with shops, residences, and convention and exhibition center

Residences: Half of the 2,306 units (lofts above stores, tower units, condos)

Two 36-story towers

Celebration Plaza, a landscaped park between canal and towers.

Phase II(4-5 years)

Construction of movie theater

Balance of residential units

Construction of office space and sports

technology center

Fishermen sue Empire Wind ... House party fatal stabbing sentencing ... What's in store with the weather Credit: Newsday

Blue wave sweeps across New York ... Judge won't dismiss 'Peaches' case ... Working Moms: Priority shift ... Fishermen sue Empire Wind

Fishermen sue Empire Wind ... House party fatal stabbing sentencing ... What's in store with the weather Credit: Newsday

Blue wave sweeps across New York ... Judge won't dismiss 'Peaches' case ... Working Moms: Priority shift ... Fishermen sue Empire Wind

Subscribe

Unlimited Digital AccessOnly 25¢for 6 months

SUBSCRIBESALE ENDS SOON | CANCEL ANYTIME